India’s Cabinet Approves Rs 14,500 Crore Scheme for 92 GWh of Grid-Scale Energy Storage
India’s Cabinet approved a Rs 14,500 crore scheme to fund 92 GWh of pumped hydro, battery and other grid-scale energy storage by 2032.
Photo by zimochen on Pexels
India’s Union Cabinet, chaired by Prime Minister Narendra Modi, approved a new India energy storage scheme on November 4, 2026, committing Rs 14,500 crore in viability gap funding (VGF) to support the development of 92 GWh of grid-scale energy storage capacity, according to a Press Information Bureau release published by PM India. The scheme covers three technologies: 60 GWh of hydro pumped storage plant (PSP) capacity, 30 GWh of battery energy storage system (BESS) capacity, and 2 GWh through alternative storage technologies, and runs from fiscal year 2026-27 to 2030-31.
The government estimates the total project investment this funding will unlock at Rs 97,600 crore, with the VGF support intended to close the gap between the cost of building storage and the revenue it can currently earn. Capacity will be allocated through a tariff-based competitive bidding process open to public and private sector electricity distribution companies (discoms) for the PSP and BESS components, while projects using alternative storage technologies can be developed by public or private entities more broadly.
Why India needs more grid-scale energy storage
The release frames the scheme around integrating more renewable power onto India’s grid without compromising reliability. It states the new capacity is equivalent to 170% of the country’s present-day grid-scale energy storage system capacity, and that it is designed to help the country reach a cumulative target of 411 GWh of grid-scale storage by 2031-32. The stated goals include facilitating large-scale renewable energy integration, ensuring round-the-clock power supply, strengthening grid stability, and reducing reliance on imported storage technology.
BESS projects under the scheme carry a minimum domestic content requirement (DCR) of 40%, a condition intended to grow India’s own battery manufacturing base rather than rely solely on imports. The release does not name the ministry administering the scheme or list specific penalties for non-compliance, and it does not quote any individual official; the only attribution given is to the Union Cabinet itself.
This is a distinct, larger programme from the Rs 3,760 crore VGF scheme for BESS that the Cabinet approved in September 2023 under the National Framework for Promoting Energy Storage Systems, which targeted a smaller 4,000 MWh (4 GWh) of battery storage alone. The new scheme is more than three times the budgetary size of the 2023 programme and, for the first time at this scale, bundles pumped hydro and alternative storage technologies into the same national VGF framework alongside batteries.
The capacity mix behind the 92 GWh target
Pumped hydro storage accounts for nearly two-thirds of the new capacity target, with batteries making up most of the remainder and alternative technologies, such as flow batteries, a small share.
| Storage technology | Capacity target | Share of 92 GWh |
|---|---|---|
| Hydro Pumped Storage Plants (PSP) | 60 GWh | 65% |
| Battery Energy Storage Systems (BESS) | 30 GWh | 33% |
| Alternative energy storage technologies | 2 GWh | 2% |
Source: PM India (Press Information Bureau), November 4, 2026.
Background
India’s push for grid-scale energy storage dates to its National Framework for Promoting Energy Storage Systems, released by the Ministry of Power in August 2023, which led to the Cabinet’s September 2023 approval of a Rs 3,760 crore VGF scheme targeting 4,000 MWh of battery storage with up to 40% of project capital cost covered. Deployment accelerated through 2026: Winssolutions.org has previously reported that India’s battery storage additions jumped 84-fold in the first half of 2026 compared with a year earlier, that NTPC’s trading arm NVVN started commercial operation of its first BESS unit, and that India separately awarded 1,344 MW of pumped hydro and its first grid-scale flow battery contract. The storage build-out runs alongside transmission investment, including the $19.3 billion Green Energy Corridor Phase-III approved to move renewable power across the grid. The new Rs 14,500 crore scheme consolidates and significantly expands that earlier, narrower effort, pairing pumped hydro with batteries and alternative technologies for the first time under one national funding mechanism, as India works toward integrating the additional solar and wind capacity needed to meet its 2030 non-fossil power targets.
Sources: PM India (Press Information Bureau); APAC News Network
Featured image: photo by zimochen on Pexels (free Pexels license).
Become a Sponsor
Our website is the heart of the mission of WINSS – it’s where we share updates, publish research, highlight community impact, and connect with supporters around the world. To keep this essential platform running, updated, and accessible, we rely on the generosity of you, who believe in our work.
We offer the option to sponsor monthly, or just once choosing the amount of your choice. If you run a company, please contact us via info@winssolutions.org.
I specialize in sustainability education, curriculum co-creation, and early-stage project strategy. At WINSS, I craft articles on sustainability, transformative AI, and related topics. When I’m not writing, you’ll find me chasing the perfect sushi roll, exploring cities around the globe, or unwinding with my dog Puffy — the world’s most loyal sidekick.