November 10, 2026

Amazon, AEP and X-energy to Explore 960 MW Small Modular Reactor Project in Indiana

Amazon, AEP and X-energy signed an agreement to explore 12 small modular reactors at a former Indiana coal plant, adding up to 960 MW of capacity.

Nuclear power plant cooling towers, representing the small modular reactor Indiana project planned by Amazon, AEP and X-energy

Photo by Sean P. Twomey on Pexels

American Electric Power (AEP), Amazon and X-energy signed a joint development agreement on October 19, 2026 to explore building up to 960 megawatts of small modular reactor (SMR) capacity at the site of a former coal plant in Sullivan County, Indiana, according to Amazon’s announcement. The project would use 12 of X-energy’s Xe-100 reactors, arranged in three groups of four, at the retired Breed Generating Station operated by AEP subsidiary Indiana Michigan Power (I&M).

How the small modular reactor project in Indiana would work

Each Xe-100 unit is a pebble-bed, high-temperature gas-cooled reactor that produces 200 megawatts of thermal output, convertible to about 80 megawatts of electricity, World Nuclear News reported. Twelve units arranged in three four-reactor groups would add up to the project’s 960 MW total. Amazon would fund the project’s development and sign a long-term power purchase agreement, becoming the plant’s first customer once it operates, while X-energy supplies the reactor technology and AEP’s I&M would operate the site.

Project detail Figure
Total planned capacity Up to 960 MW
Number of Xe-100 reactors 12, in three groups of four
Output per reactor 80 MWe (200 MWth)
Estimated construction jobs About 1,000
Estimated permanent jobs About 100
Site Former Breed Generating Station, Sullivan County, Indiana
Roles of AEP, X-energy and Amazon in the planned Indiana small modular reactor project AEP / Indiana Michigan Power Site and plant operations at former Breed station X-energy Xe-100 reactor design and TRISO-X fuel supply Amazon Project funding and long-term power purchase Up to 960 MW planned Sullivan County, Indiana Evaluation stage; proceeds only after a final investment decision by AEP and X-energy
How AEP, X-energy and Amazon divide roles in the proposed Indiana small modular reactor project. Source: Amazon and World Nuclear News, October 19, 2026.

Still at the evaluation stage

The agreement is a joint development pact, and the project moves forward only if AEP and X-energy reach a final investment decision, World Nuclear News reported. Neither company has set a construction start date or a commissioning date, and Amazon has not disclosed the length of its power purchase agreement, saying only that the deal covers project costs “for the duration of the contract.” Sullivan County recently joined the Indiana Advanced Nuclear Ready Communities Program, World Nuclear News reported.

AEP chairman and CEO Bill Fehrman said advanced nuclear energy “has the potential to provide dependable power for over half a century.” X-energy CEO J Clay Sell said the project “pairs AEP’s 50 years of excellence in nuclear operations with the world-class expertise of Amazon.”

Part of a larger nuclear buildout for data centers

The Indiana proposal adds to a wider push by technology companies to secure new nuclear generation for data centers. Amazon separately signed a 20-year deal with Constellation Energy for power from the Calvert Cliffs nuclear plant in Maryland, and AEP itself is building a $4 billion, 702 MW Bloom fuel cell plant in Wyoming to power a Google data center. Both deals, like the Indiana SMR proposal, sit within a broader rebound in nuclear investment now extending to newer reactor designs such as X-energy’s Xe-100.

Background: X-energy’s Xe-100 reactor and development pipeline

X-energy, founded in 2009 by chairman Kam Ghaffarian and based in Rockville, Maryland, designed the Xe-100 pebble-bed reactor planned for the Indiana project. The reactor uses TRISO fuel pebbles enriched to under 20 percent (HALEU), supplied through the company’s TRISO-X subsidiary, which received a 40-year US Nuclear Regulatory Commission license in February 2026 to manufacture the fuel. X-energy’s first Xe-100 deployment is planned at Dow’s Long Mott Generating Station on the US Gulf Coast, and the company is also developing the Cascade Advanced Energy Facility in Washington state with Energy Northwest and Amazon, expected to begin operating in the mid-2030s. X-energy completed what it called the largest nuclear IPO on record on the Nasdaq in April 2026, raising more than $1 billion. Amazon has backed X-energy since 2024, when it joined the Washington state project to help fund four Xe-100 reactors, part of a joint goal with X-energy to add more than 5 gigawatts of new US nuclear capacity by 2039. The Indiana proposal would be a third major X-energy effort alongside Washington and the Gulf Coast, and its first with AEP, whose Indiana Michigan Power subsidiary has operated the Donald C. Cook nuclear plant for more than 50 years.


Sources: Amazon; World Nuclear News; POWER Magazine

Featured image: photo by Sean P. Twomey on Pexels (free Pexels license).


Become a Sponsor

Our website is the heart of the mission of WINSS – it’s where we share updates, publish research, highlight community impact, and connect with supporters around the world. To keep this essential platform running, updated, and accessible, we rely on the generosity of you, who believe in our work.

We offer the option to sponsor monthly, or just once choosing the amount of your choice. If you run a company, please contact us via info@winssolutions.org.

Select a Donation Option (USD)

Enter Donation Amount (USD)

What do you feel about this?