AEP to Build $4 Billion, 702 MW Bloom Fuel Cell Plant in Wyoming to Power Google Data Center
AEP will build a $4 billion, 702 MW Bloom Energy fuel cell plant in Wyoming to supply low-carbon power to Google under a 20-year deal.
Photo by Petr Ganaj on Pexels
American Electric Power (AEP) will build a $4 billion, 702 megawatt fuel cell power plant near Cheyenne, Wyoming, to supply low-carbon electricity to Google under a 20-year power purchase agreement, ESG Today and Data Center Dynamics reported on October 14 and October 15, 2026. The project will use fuel cell technology from Bloom Energy and is designed to run without burning natural gas on site.
How the deal is structured
AEP will develop and own the project through Cheyenne Fuel Cell, a subsidiary in which AEP holds about 92 percent, with the remaining roughly 8 percent held by funds advised by Basalt Infrastructure Partners, according to Data Center Dynamics. Google will purchase the plant’s output under the 20-year agreement. AEP President and CEO Bill Fehrman said the company is “bringing together new technologies and strong partnerships” to deliver energy solutions quickly and at scale, according to ESG Today.
Construction is scheduled to begin in 2026, with the plant expected to be fully operational by the end of 2028, both outlets reported. The companies say the project plans to add carbon capture equipment to reach near-zero-emissions power generation, beyond the baseline advantage of avoiding on-site natural gas combustion that conventional gas turbines would otherwise require.
Why Google is adding fuel cells in Wyoming
The power is intended for a Google data center development near Cheyenne. Data Center Dynamics reported that Google is building a 2.7 gigawatt data center on a 716-acre site in the Switchgrass Industrial Park, a project that first emerged in July 2026 and is slated for completion by 2031. South Dakota-based utility Black Hills has separately reached agreements to supply electricity to the same Cheyenne data center development, indicating Google is drawing on more than one power source for the site.
Bloom Energy’s role extends beyond this single deal. Data Center Dynamics reported that AEP’s broader supply agreement with Bloom covers up to 1 gigawatt of fuel cell capacity, and that Bloom has separate data center supply deals with Nebius, signed in May 2026, an expanded Oracle agreement covering up to 2.8 gigawatts with an initial 1.2 gigawatt deployment underway, and Equinix, covering 19 data centers and more than 100 megawatts.
| AEP-Google Wyoming fuel cell deal | Detail |
|---|---|
| Capacity | 702 MW |
| Investment | $4 billion |
| PPA term | 20 years |
| Location | Near Cheyenne, Wyoming |
| Fuel cell supplier | Bloom Energy |
| Project vehicle | Cheyenne Fuel Cell (AEP ~92%, Basalt Infrastructure Partners funds ~8%) |
| Construction start | 2026 |
| Full operation target | End of 2028 |
| AEP-Bloom broader supply agreement | Up to 1 GW |
Part of a wider pattern of data center power deals
The AEP-Google agreement adds to a run of long-term power deals utilities and developers have struck with major cloud and AI companies to secure dedicated, often low-carbon generation for data centers. Winss Solutions has tracked several related deals, including Fervo Energy’s 396 MW enhanced geothermal power agreement with Google for a Utah data center, Google and Cypress Creek breaking ground on the 2.5 GW Steel River Energy Center solar and storage project in Arkansas, and RWE’s 433 MW wind power purchase agreement with Oracle to supply Texas data centers. Unlike those solar, wind and geothermal deals, the AEP-Bloom project relies on fuel cells, a technology that can run continuously regardless of weather, which utilities are increasingly pairing with carbon capture plans to court power-hungry data center customers without directly burning natural gas on site.
Background: AEP and Bloom Energy
American Electric Power is an Ohio-based electric utility holding company serving millions of customers across multiple US states. Bloom Energy is a US fuel cell manufacturer whose solid oxide fuel cell systems convert natural gas or other fuels into electricity through an electrochemical process rather than combustion, a distinction the companies say allows the Wyoming project to avoid on-site gas burning before carbon capture equipment is added. The Cheyenne project follows a string of Bloom Energy agreements with data center operators and cloud providers through 2026, as utilities and technology companies sought generation that could be built faster than new transmission lines or large-scale battery storage, while AEP’s $4 billion commitment represents one of its largest single generation investments tied to a technology company’s power demand.
Sources: ESG Today; Data Center Dynamics
Featured image: photo by Petr Ganaj on Pexels (free Pexels license).
Become a Sponsor
Our website is the heart of the mission of WINSS – it’s where we share updates, publish research, highlight community impact, and connect with supporters around the world. To keep this essential platform running, updated, and accessible, we rely on the generosity of you, who believe in our work.
We offer the option to sponsor monthly, or just once choosing the amount of your choice. If you run a company, please contact us via info@winssolutions.org.
I specialize in sustainability education, curriculum co-creation, and early-stage project strategy. At WINSS, I craft articles on sustainability, transformative AI, and related topics. When I’m not writing, you’ll find me chasing the perfect sushi roll, exploring cities around the globe, or unwinding with my dog Puffy — the world’s most loyal sidekick.